[BD-29] Learning Sequence Experience Improvements
Blended Project ID | BD-29 |
edX Product Lead | @Marco Morales (Deactivated) |
edX Technical Primary | @Dave Ormsbee (Deactivated) (@David Joy (Deactivated) as secondary) |
Provider | OpenCraft |
Provider Lead | @Piotr Surowiec |
Calendly Scheduling Link | None used. |
Slack Channel | edx-opencraft |
Meeting Cadence / Preference | none, relied on async updates after kickoff review. |
Action Item Tracking | Use Slack first; can also add action items on project status pages or provider status page |
Escalation Path | https://openedx.atlassian.net/wiki/spaces/COMM/pages/1529676506 Escalation path outlined here |
Relevant Discovery Documents | NA |
Status Update Frequency | biweekly |
Target Completion Date | September |
~Dev Hours Per Sprint Expected | 0 (Done) |
Total Hours Used | 100% - 11/17 |
Blended Project Epic (Tracks pull requests) |
Open Action Items
Status Updates
Time Frame | Updates & Actions Needed | ~Hours |
---|---|---|
Enter weekly/bi-weekly timeframe for updates (ex. June 15 - June 19) | Insert actions by selecting checkbox icon in page editor |
|
Initial status | We scheduled all tickets except: for the upcoming sprint (June 15 - June 29). |
|
June 15 - June 29 | Work done this sprint: Ongoing work from this sprint: Temporarily blocked: Removed: Moved to the next sprint: Work scheduled for the next sprint: Work postponed to future sprints: | ~213.4h |
June 29 - July 13 | Work done this sprint: Ongoing work from this sprint: Temporarily blocked: | ~327.4h |
July 13 - July 27 | Work completed this sprint: Ongoing review: Waiting for review: Blocked: Ongoing work from this sprint: Removed: Moved to the future sprint: | ~429h |
July 27 - August 10 | Work completed this sprint: Waiting for review: Blocked:
Ongoing work from this sprint: | ~485h |
August 10 - August 24 | Work completed this sprint:
Waiting to be merged: Waiting for review: Blocked:
Ongoing work from this sprint: | ~510h |
August 24 - September 7 | Work completed this sprint: Waiting to be merged:
Waiting for review: Ongoing unblocked work: Archived: | ~530h |
September 7 - September 21 | Work completed this sprint: Waiting for review: | ~550h |
September 21 - October 5 | Work completed this sprint:
Ongoing review: | ~555h |
October 5 - October 19 | Done: Waiting for review: | ~558h |
October 20 - November 2 | Waiting for review: | ~560h |
November 3 - November 16 | Done: | 565.2h |
Relevant Jira Stories, Tasks, Bugs
This section links to all the development stories, tasks, and bugs connected to the single (or multiple) epics used to track the work on the Open edX JIRA site.
/
Relevant Pull Requests linked to Blended Project Epic
This section will link to the edX internal Blended project epic, and contains all Pull Requests related to this Blended Project.