How We Estimate

To point tasks, the team uses a Fibonacci sequence which maps roughly to the amount of time a task will take (which maps roughly to the complexity of the task). The pointing scale is as follows:

Points

Rough Time

Task Will Take

Points

Rough Time

Task Will Take

1

1 hour (well-defined, short task)

2

4 hours

3

1 day

5

2.5 days

8

5 days

13

2 weeks