I. Context, data, and highlights 🏅

  • The Sumac master branch was cut on 10/24, two weeks later than originally planned.

  • The testing process was completed to 96.4% and took 7 weeks.

  • Due to some deployment issues discovered with MongoDB index creation on 2U Forums v2, the Sumac release was delayed one week and successfully released on 16/12.

II. Successes and achievements 🏅

III. We should keep ✅

IV. What didn’t we do so well, and what could we have done to do better ❌

Product

Testing

Bug triage and fixing

Security

Release notes

Backports

VI. Action Items for Sumac release 📈

Product

Testing

Bug triage and fixing

Security

Backports

Release notes