Milestone Goal(s)

Hour Estimate Low

Hour Estimate High

Actual Hours (Week Starting on)

NOTES (Date collected)

Feb 27

Mar 6

Mar 13

Mar 20

Mar 27

Apr 3

Apr 10

Apr 17

Apr 24

May 1

May 8

May 15

May 22

May 28

June 1 to July 31

TOTAL

1.1

Conform a diverse set of 10 repositories including MFEs, XBlocks, libraries and backend components to ensure deliverables are matching expectations.

Push the strings to the openedx-translations repo.

Ensure all contributors are up to date with the OEP core proposal and its detailed discussion.

20

40

3:23

12:04

9:20

8:00

8:30

4:00

6:00

51

  • [Omar @ Apr 3] Initial i18n work is mostly discovery and experimentation therefore there has been a bit of overrun.

1.2

Conform 25 more remaining repositories with documentation updated.

60

90

7:00

4:30

5:00

15:30

27

1.3

Conform all remaining 32 repositories with documentation updated.

90

120

7:00

24:00

19:00

5:30

10:00

16:30

6:00

71

1.4

Update docs and code on cookie cutters, SDKs and template repositories.

15

25

2.1

Complete workflows of openedx-atlas and ensure it works

45

65

6:00

9:00

20:00

11:00

4:00

10:00

9:00

65

2.2

Update documentaiton of openedx-atlas in devstack and cookie cutter repositories

20

30

Sum

~250

~370

232