Summary of work
This summary reflects progress to .
Status | ||||
---|---|---|---|---|
|
3 new components, 1 component update, and a new svg icon library
...
Status | ||||
---|---|---|---|---|
|
1 new component
...
Roadmap
Info |
---|
A change in plans. Adam B has learned over the fall that if your plan has 4 phases, that’s too many phases. The roadmap now reflects Phase 1 and 2 (design and reimplementation of existing components) and moving forward components will be reflected in epics below. These epics are currently open ended. Adam B. will work to better clarify due dates and timelines moving forward. |
...