Time Frame | Updates & Actions Needed | ~Hours |
---|---|---|
June 15 - June 29 | Work planned for next week:
On TNL-7280, I'll add a Tasks related to the grades implementation to the LTI improvements epic since we agreed to avoid this middle step of doing the read-only implementation and will focus on a feature-complete delivery. | We've spent ~106.5 h of the 105 hours of development time. |
June 29 - July 13 | Work done:
Work planned for next week:
| We've spent ~116 h of the 105 hours of development time. |
July 13 - July 27 | Some deployment bugs were fixed, and the updated block is now tagged and deployed. Waiting on feedback from edX and better clarity about documentation rework. | We've spent ~126 h of the 105 hours of development time. |