Open Action Items
Task report
Looking good, no incomplete tasks.
Status Updates
Time Frame | Updates & Actions Needed | ~Hours |
---|---|---|
July 01 - July 02 |
| 6 |
July 06 - July 10 |
| 42 |
July 11 - July 13 |
| 20 |
July 03 - July 29 |
| 150 |
July 16 - 10 September |
| 90 |
July 16 - 12 Augst |
| 12 |
Relevant Jira Stories, Tasks, Bugs
This section will link to all the development stories, tasks, and bugs connected to the single (or multiple) epics used to track the work on the Open edX JIRA site.
Relevant Pull Requests linked to Blended Project Epic