Blended Project ID

BD-26

edX Product Lead

Marco Morales (Deactivated)

edX Technical Primary

Zach Hancock


Provider

Racoon Gang

Provider Lead

Igor Degtiarov

Calendly Scheduling Link

TBD

Slack Channel

  • external-openedx-edx-raccoon-gang (on edX side)

  • edx-shared-raccoon-gang (on Open edX side)

  • shared_open-edx (on RG side)

Meeting Cadence / Preference

  • Cadence

    • 2x a week (in March and April)

    • Then 1x a week (in May, June, and July)

cancelling/shortening meetings as appropriate

Action Item Tracking

Small action items from meetings go on this page.

Use slack first, can also add action items on project status pages or provider status page

Escalation Path

Relevant Discovery Documents

Scoping Document, Technical Design Document,
BD-26 Project charter
BD-26 Technical documentation

Status Update Frequency

biweekly

Target Completion Date

July 2021

Expected Dev Hours In Upcoming Months

970 hours

Total Hours Used

100% - 5/28

Blended Project Epic (Tracks pull requests)

https://openedx.atlassian.net/browse/EDUCATOR-5646

Provider Main Developers

Igor Degtiarov Vladas Tamoshaitis Evgeniy Sagirov Viktor Rusakov

Project Scrum Board

https://openedx.atlassian.net/secure/RapidBoard.jspa?rapidView=683

Open Action Items

Task report

Looking good, no incomplete tasks.

Status Updates

Time Frame

Updates & Actions Needed

~Hours

-

Work done this sprint:

Work in progress issues from the previous sprint fixed and tested.

We’ve spent in sprint 13 hours.

-

Work done this sprint:
Testing and communications. Several issues were fixed:

https://openedx.atlassian.net/browse/EDUCATOR-5893

https://openedx.atlassian.net/browse/EDUCATOR-5892

https://openedx.atlassian.net/browse/EDUCATOR-5842

https://openedx.atlassian.net/browse/EDUCATOR-5828

Two new issues were found.

Work in progress:

https://openedx.atlassian.net/browse/EDUCATOR-5909

https://openedx.atlassian.net/browse/EDUCATOR-5908

We’ve spent in sprint 27 hours.

-

Work done this sprint:

Fixed and merged all PRs thaht were in progress

Completed with the feature Time limited bar for non-sequence pages

https://openedx.atlassian.net/browse/EDUCATOR-5874

Complete testing for time limited/onboarding/proctoring special exams on edX staging

Work in progress:
Minor enchancement:
https://openedx.atlassian.net/browse/EDUCATOR-5842

We’ve spent in sprint 60 hours.

-

Work done this sprint:

Timed Exam feature is tested on edX Stage, new issues were found and part of them are already fixed.

Onbording/Practice exam is tested on the RG Dev.

Proctoring exam is tested on RG Dev.

Work in progress:

Testing Onbording/Practice exam on edX Stage is in progress.

Fixing issues:

https://openedx.atlassian.net/browse/EDUCATOR-5864

https://openedx.atlassian.net/browse/EDUCATOR-5854

https://openedx.atlassian.net/browse/EDUCATOR-5866

https://openedx.atlassian.net/browse/EDUCATOR-5861

Adding new functionality:
https://openedx.atlassian.net/browse/EDUCATOR-5857

https://openedx.atlassian.net/browse/EDUCATOR-5860

We’ve spent in sprint 55 83 (Improved after gathering all effort) hours.

-

Work done this sprint:

  • Waffle Flag to enable/disable exams that are required proctoring provider

  • Onboarding exam feature is completed

Work in progress:

We’ve spent in sprint 188 hours

~ 125% - 6/14 (from initial estimations)

~ 90% - 6/14 (from additionally-agreed hours)

-

Work done this sprint:

  • Proctored exam is finished, though the Waffel flag to enable/disable proctored exams is in progress still.

  • The timed exam functionality is covered with the tests.

  • Mockprock provider was set up on the dev instance.

Work in progress:

We’ve spent in sprint 232 hours

~ 100% - 5/28

-

Work done this sprint:

  • Timer feature Implementation was done.

  • BLENDED-835 merged

Work in progress:

  • Proctored exam feature has been started
    EDUCATOR-5672

    • Investigating of how existed provider’s JS Worker could be supported in the react.

    • Working on required API endpoints for the proctored exam on backend side.

    • Working on proctored instruction pages

  • Setup Mockprock provider for local development.

We’ve spent in sprint 175 hours

~ 68% - 5/14

​-

Work done this sprint:

  • Timed exam implementation was done.

  • Investigation work on Timed exam and Timer feature was completed.

  • BLENDED-832 merged.

Work in progress:

Finishing Timer feature Implementation.

https://openedx.atlassian.net/browse/BLENDED-835

We’ve spent in sprint 156 hours

~ 45% - 4/30

​-

Work done this sprint:

  • Internal RG repos created and configured.

  • Part of the initial investigation work was completed.

  • POC for rendering exam sequence in MFE-AL

Work in progress:

Start working on TimedExam Implementation in frontend-lib-special-exams

We’ve spent in sprint 143 hours

~ 25% - 4/16

​-

Work done this sprint:

  • Team kick-off and onboarding

  • Grooming tickets for the next sprint.

Work in progress:

  • Preparing internal RG repositories for the projects

  • Preparing local development infrustructure

We’ve spent in sprint 36 hours

5% - 4/2

Meeting Notes

Date

Attendees

Notes

03/23/2021

Zach Hancock Simon Chen Igor Degtiarov Peter Koblyakov

Kick off preparation meeting

03/29/2021

Zach Hancock Simon Chen Igor Degtiarov Alison Langston Bianca Severino Michael Roytman

Alona Sedykh

Kick off meeting

  • Introductions (20 min)

  • Discuss project goals and scopes (10 min)

  • Align on engineering process (10 min)

https://openedx.atlassian.net/secure/RapidBoard.jspa?rapidView=683

  • Technical Design Q and A https://docs.google.com/document/d/1hS_WCLglzZIYZmKYq776n5qs7Kmi2is0R6dvcTj-lbs/edit (10 min)

Resources

  • TBD

Retrospective

Start doing

Things to improve

Keep doing

  • Combining dependent features into one PR

  • Showing demo to tester before code review

  • Preparing in advance before the demo, checking that the environment is working correctly

  • detailed ticket grooming during the planning and work break down structure

  • to have consistent team during the project

  • QA team should be involved and visible (responsible) from the start of development not only at the “final” project milestones

  • active conversation regarding budget overspends, savings

  • depending changes in branches

  • Sharing progress about tasks at stand-ups.


  • Answering questions quickly.

  • Clear communication

  • good dev work (especially during July) - estimation and executing

  • quick onboarding of developers

  • the periodicity of demo session

  • scope breakdown

  • testing on edX side

  • RG dev environment

  • budget monitoring

Action items

Relevant Jira EPICs

key summary type created updated status due
Loading...
Refresh

Relevant Pull Requests linked to Blended Project Epic

This section will link to the edX internal Blended project epic, and contains all Pull Requests related to this Blended Project.

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

  • No labels