Milestone 1: User stories and problem definition

  • Deliverables: A list of clearly articulated user stories (not prioritized) that appropriately reflect the problem(s) the modular learning initiative will solve.

Sub-milestones:

  • Draft user stories
  • Map user stories, v1
  • Solicit stakeholder feedback (target 6-8 superusers/clients) [In-progress, target Oct 15 for completion]
  • Integrate feedback
  • Finalize user stories

Milestone 2: User story mapping and prioritization [partially already complete in Milestone 1]

  • Deliverables: A clearly articulated opinion on which user stories will be prioritized to guide subsequent milestones.

  • Define prioritization criteria (both product and tech perspective)
  • Identify subset of user stories to prioritize
  • Tweak user story map to reflect priority, v2

Milestone 3: Approach speccing

  • Deliverables: An approach document that articulates possible approaches and solutions.

  • Write proposed Approach Spec
  • Write MVP Tech Spec (based on prioritized user stories)
  • Create “Consumer Review 2.0” = Open all documentation for community review and input

Milestone 4: Wire Framing and user journey definition

  • Deliverables: Mock wire frames or design prototypes that outline the user journey based on the approach documentation.

  • Design low-fi UX frames [IN PROGRESS]
  • Light touch user feedback/usability testing

Milestone 5: Tech/arch Prototype

  • Deliverables: Low-fi tech prototype that can 1) serve as a proof of concept and 2) guide effort estimates for broader implementation

  • Tech spec
  • MVP Milestone planning [IN PROGRESS]

Milestone 6: Product Requirement Documentation*

  • Deliverable: Product Requirement Documentation that includes Overview of the initiative

    • Articulation of the problem(s) and the opportunity

    • Market evidence + user stories

    • Approach and solution

    • Wire frames

    • Any risks and dependencies

  • Final PRD

*As the scope of this project evolved, PRD will be focused on Phase 1 and Phase 2, which future PRD work to follow incrementally.