Sumac.1 Retrospective 🌳⏪
Sumac.1 Retrospective 🌳⏪
I. Context, data, and highlights 🏅
The Sumac master branch was cut on 10/24, two weeks later than originally planned.
The testing process was completed to 96.4% and took 7 weeks.
Due to some deployment issues discovered with MongoDB index creation on 2U Forums v2, the Sumac release was delayed one week and successfully released on 16/12.
II. Successes and achievements 🏅
III. We should keep ✅
IV. What didn’t we do so well, and what could we have done to do better ❌
Product
Testing
Bug triage and fixing
Security
Release notes
Backports
VI. Action Items for Teak release 📈
Product
Testing
Bug triage and fixing
Security
Backports
Release notes