[BD-24] Opencraft Status Updates
Time Frame | Updates & Actions Needed | ~Hours |
---|---|---|
June 29 - July 13 | The implementation of the LTI Advantage services will start this sprint. Tickets in progress:
New tickets: | We've used 29.3 hours of the the 400 hour budget. 7.3% - 6/29 |
July 13 - July 27 | Some of the work from last sprint was pushed back due to the high priority LSE tickets. We’re ramping up hours starting this sprint to implement 2 LTI advantage services. Tickets in progress:
New tickets:
| We've used 41.1 hours of the the 400 hour budget. 10% - 7/13 |
July 27 - August 10 | Tasks from last sprint waiting for edX review:
New tasks: As per @Marco Morales (Deactivated)'s request, we’re pausing this epic for 1 to 2 sprints until the TNL and OpenCraft team have more availability. This pause will allow both teams to work on less projects at the same time. | We've used 67.5 hours of the the 400 hour budget. |
August 10 - August 24 | This is the second sprint of the pause. See the update above. Tasks from last sprint waiting for edX review and discussions:
| We've used 74.3 hours of the the 400 hour budget. |
August 24 - September 7 | Epic paused - addressing remaining comments and merging open PRs. | We've used 73.8 hours of the the 400 hour budget. |
September 7 - September 21 | Tasks from last sprint waiting for edX review:
Tasks that to be finished:
Notes: We need to wrap up TNL-7318, since it blocks most of the other tasks. It adds support for the first LTI advantage service (AGS), as well as lays the groundwork to implement other services. Authorization and Authentication will be implemented here and be reused by the other services. | We've used 83.7 hours of the the 400 hour budget. |
September 22 - October 5 | What's left to do? https://openedx.atlassian.net/browse/TNL-7318 is still ongoing, but to unblock the project, I'll create the follow up tasks and ask people to branch off the work being done there. We can implement the other LTI AGS endpoints and move forward with other LTI Advantage extensions implementation. Are all upcoming stories that we should work on in the next week or two created and in the correct upcoming sprint? Tickets in progress: Tickets waiting for edX review: Tickets for next sprint: Tickets for sprint 231:
| We've used 100.2 hours of the the 390 hour budget. |
October 5 - October 19 | Tickets waiting for edX review:
Tickets blocked on TNL-7318 (but almost ready for review): Tickets in progress: Tickets in discovery:
| We've used 132.1 hours of the the 390 hour budget. |
October 20 - November 2 | Tickets in progress:
Tickets postponed: Tickets waiting for edX review:
| We've used 168 hours of the the 390 hour budget. |
November 3 - November 16 | New tickets:
Tickets in progress:
| We've used 196.7 hours of the the 390 hour budget. |
November 17 - November 30 |
| We've used 214 hours of the the 390 hour budget |
November 30 - December 14 | New tickets: For next sprint:
| We've used 235 hours of the the 390 hour budget |
December 14 - December 29 | In progress: Sprint 236:
Tickets for 237: Tickets for future sprints:
Waiting edX review: | We've used 288 hours of the the 380 hour budget. |
December 29 - January 11 | In progress:
Tickets for 237: Tickets for future sprints:
Waiting edX review: | We've used 293 hours of the the 380 hour budget. |
January 11 - January 25 | TBD | - |
January 26 - February 8 | New work: Ready to review: Next sprint:
| We've used 318 hours of the the 380 hour budget (62h left). |
February 8 - February 22 | Tickets blocked on other work:
Waiting for upstream review: Next sprint: Future sprints:
| We've used 341.5 hours of the the 380 hour budget. |
February 22 - March 8 | Waiting for edX review: Next sprint:
| We've used 346 hours of the the 380 hour budget. |